Off-grid solar system design: 3 kW and 5 kW systems for the UK, USA and Australia
Two complete stand-alone solar systems on a 48 V lithium battery bank, from a 3 kW starter system to 5 kW and beyond. Includes the protection and cable schedule, month-by-month PVGIS simulations for six locations, generator planning, earthing, surge protection and the rules in each country: BS 7671, NEC Articles 690, 706 and 710, and AS/NZS 4509, 5033, 5139 and 3000.
By Michael Johnson · Updated 18 November 2026 · How we check our guides · Open the wiring diagram full size
- In Australia, it must be done by a licensed electrician.
- In the UK, it must be certified (EIC) and usually notified under Building Regulations.
- In the USA, it normally needs a permit and an inspection.
1. Is there a legal size limit?
No country sets a maximum size for a system that is truly off-grid. The power limits people quote apply only to systems connected to the public grid:
| Country | Limit you may have heard of | Does it apply off-grid? | What does change as an off-grid system grows |
|---|---|---|---|
| UK | ENA EREC G98 (micro-generation up to 16 A per phase, about 3.68 kW, connect and notify) and G99 (larger systems, DNO approval first). | No. G98 only covers generators "designed to normally operate in parallel with" the public low-voltage network. It expressly excludes islanded installations (scope, clause 2.10). A property with no grid connection at all falls under neither G98 nor G99. The exception: if the property also has a grid supply and the system can switch between grid and island (a backup or changeover arrangement), that islanded operation falls under G99. Speak to the DNO before connecting anything to a grid-fed installation. | Battery location rules (PAS 63100). Building Regulations notification. Inverter paralleling or three-phase above about 10 kW. |
| Australia | Network export limits, often 5 kW per phase (set by each distributor under AS/NZS 4777). | No. They apply only to grid-connected inverters. | Battery arc-flash energy (AS/NZS 5139, as applied in the SEIAPI guideline): above 4 cal/cm², not in a building with habitable rooms; above 8 cal/cm², split into segments; domestic below 40 cal/cm². |
| USA | Utility interconnection limits and NEC 705 "120% rule". | No. A stand-alone system falls under NEC Article 710, not 705. | Residential battery limits (NFPA 855 and IRC R328): 20 kWh per ESS unit. 40 kWh in total in a utility or storage room, and 80 kWh in total in a garage, on an outside wall or in a detached structure. |
So this document follows your brief: a 3 kW system scaled up to 5 kW. scaling beyond 5 kW shows how to go further and which rules start to bite.
2. The two reference systems
| Part | 3 kW system | 5 kW system | Notes |
|---|---|---|---|
| Inverter/charger | 48 V, 3 kVA class (e.g. Victron MultiPlus-II 48/3000/35) | 48 V, 5 kVA class (e.g. MultiPlus-II 48/5000/70) | VA is not continuous watts. The 48/3000 gives about 2.4 kW continuous at 25 °C and the 48/5000 about 4 kW. If you need a full 3 kW or 5 kW all day, pick the next size up. USA: the 3 kW system uses the 120 V model. The 120 V 48/5000 has a 120 V output only, so the US 5 kW system uses two 120 V 48/3000 units stacked for 120/240 V split phase (6 kVA, about 4.8 kW continuous), or one native split-phase inverter. |
| Battery | 2 × 5 kWh 48 V (51.2 V) LiFePO4 = 10 kWh | 3 × 5 kWh = 15 kWh | Rack or wall modules with a BMS that talks to the inverter. USA: each ESS unit ≤ 20 kWh, listed to UL 9540. |
| Solar array | 8 × 450 W = 3.6 kWp (2 strings of 4) | 16 × 450 W = 7.2 kWp (2 arrays, each 2 strings of 4) | Off-grid arrays are oversized compared with the inverter so they still charge the battery in poor weather. |
| Charge controller | 1 × MPPT 250/70 | 2 × MPPT 250/70 | Each controller is 70 A, about 4 kW nominal at 48 V. 250 V absolute maximum PV voltage (245 V operating). Maximum PV short-circuit current 70 A. |
| Generator (optional) | about 3–5 kVA | about 6–8 kVA | Connects to the inverter's AC input for winter top-up. |
| AC output | Inverting at its continuous rating: UK/AU 2.4 kW at 230 V ≈ 10.4 A; USA 2.4 kW at 120 V ≈ 20 A. Generator pass-through: up to the transfer switch rating (32 A UK/AU, 50 A USA). | Inverting at its continuous rating: UK/AU 4 kW at 230 V ≈ 17.4 A; USA 2 × 2.4 kW split phase ≈ 20 A per leg. Generator pass-through: up to 50 A. | Feeds a normal consumer unit, switchboard or panel. When the generator runs, its power passes through the inverter, up to the transfer switch rating, so the output breaker and cable are sized for that (the protection schedule). |
The example module is a typical 450 W panel: Voc 49.5 V, Isc 11.6 A, Vmp 41.5 V, Imp 10.85 A, Voc temperature coefficient −0.27 %/°C, maximum series fuse 20 A. Redo every calculation with your own module's datasheet.
3. Wiring diagram
4. Design calculations
PV string voltage (cold weather)
PV open-circuit voltage rises as the panels get colder. Four panels in series give 4 × 49.5 = 198 V at 25 °C. Correct this for the coldest morning at the site:
| Site minimum | Method | String Voc | Under 245 V? |
|---|---|---|---|
| UK, −10 °C | 198 × (1 + 0.0027 × 35) | 216.7 V | Yes |
| Australia, −10 °C (inland/alpine) | AS/NZS 5033 coefficient method, or the generic factor table in the SEIAPI guideline | 216.7 V by coefficient. About 226 V by the generic table. | Yes |
| USA, −40 °C (coldest states) | NEC 690.7(A)(1), module coefficient, ASHRAE extreme minimum | 232.8 V | Yes, just, using the module coefficient method. The alternative NEC 690.7(A) table factor (1.25 at −40 °C) gives 247.5 V, which fails. At colder sites, or with higher-Voc modules, use 3 in series. |
PV current, cables and string fuses
- Cable current: PV string cables must carry at least 1.25 × Isc = 14.5 A (UK and Australia). The US applies 125% twice (NEC 690.8), giving 1.56 × Isc = 18.1 A. A 6 mm² PV cable (10 AWG PV wire in the US) covers both. Over a 20 m one-way run it drops about 1.25 V, or 0.75%.
- String fuses: with only two strings per MPPT, a fault in one string can only be fed by the other. That current (11.6 A) is below the module's 20 A maximum series fuse rating, so no string fuses are needed. With three or more strings in parallel, fit gPV fuses in each string. The usual rule is between 1.5 and 2.4 × Isc and no more than the module's maximum series fuse rating, here 20 A gPV. US NEC 690.9 requires at least 1.56 × Isc, which also gives 20 A.
- PV DC isolator: one 2-pole PV-rated DC switch-disconnector per array, next to the controller. Rate it above the cold Voc (use 250 V DC or more) and above 1.25 × the array Isc (about 29 A). A 32 A part suits this.
Battery current
| 3 kW system | 5 kW system | |
|---|---|---|
| Inverter DC draw used for cable and fuse sizing. Assumes 3 kW / 5 kW of AC output (a margin above the 2.4 kW / 4 kW continuous real-power rating at 25 °C), a low battery voltage of 44 V and 94% efficiency: DC amps = W ÷ (44 × 0.94). At the 2.4 kW / 4 kW continuous rating it's about 58 A / 97 A. The 3,000 VA / 5,000 VA figures are the continuous apparent-power ratings; peak (surge) ratings are listed separately on the datasheet | ≈ 73 A | ≈ 121 A |
| Maximum charge current (MPPTs + inverter charger) | 70 + 35 = 105 A | 140 + 70 = 210 A. Limit it to what the battery accepts with the inverter's charge-current setting (DVCC). |
| Inverter fuse F1 and cable C2 (Victron table, cable runs up to 5 m) | 125 A, 35 mm² | 200 A, 70 mm² |
| Main battery fuse F7 and cable C4 (junction → isolator → busbar) | 160 A Class T, 50 mm² | 250 A Class T, 95 mm² |
| Per-battery fuses F4–F6 | 125 A each, 35 mm² leads | 125 A each, 35 mm² leads |
| Battery-cable voltage drop (2 m run) | ≈ 0.14 V (0.3%) | ≈ 0.12 V (0.3%) |
Why there's a main fuse as well as a fuse on each battery: fuses in parallel add up. Three 125 A battery fuses could let 375 A into the shared cable without any of them blowing. F7 protects the shared cable and the isolator. The breaking capacity of every DC fuse must also exceed the combined short-circuit current of the paralleled batteries. AS/NZS 5139 Amendment 1 (December 2025) now says this explicitly. Ask the battery maker for the short-circuit figure. The per-battery devices F4–F6 and the main fuse F7 must each have the full breaking capacity themselves: use Class T fuses (20 kA), NH DC fuses, or the battery's own rated DC breaker. The busbar fuses F1–F3 (MEGA fuses in a Lynx Distributor, for example) have a lower breaking capacity. They rely on the upstream Class T fuse F7 as backup protection, so confirm that combination with the maker. Otherwise use Class T or NH holders for F1–F3 too.
5. Protection and cable schedule
Metric sizes are for 90 °C single-core copper run singly (not bundled), which is how Victron specifies its battery cables. US sizes are copper rated at 75 °C (NEC Table 310.16) unless stated, and never smaller than the metric size. The exception is PV wire, which is sized to NEC 690.8 (10 AWG is ample for 18.1 A).
| Ref | Circuit | 3 kW device / cable | 5 kW device / cable | US cable (3 kW / 5 kW) |
|---|---|---|---|---|
| C1 | PV strings → isolator → MPPT | No fuse with 2 strings. 6 mm² H1Z2Z2-K (EN 50618) | Same, per array | 10 AWG PV wire (UL 4703) |
| F2, F3 | MPPT → busbar | 100 A, 25 mm² | 100 A each, 25 mm² | 2 AWG (115 A) |
| F1 / C2 | Busbar → inverter | 125 A, 35 mm² | 200 A, 70 mm² | 1 AWG (130 A) / split phase: 2 × (125 A, 1 AWG), one per inverter |
| F7 / C4 | Battery junction → isolator → busbar | 160 A Class T, 50 mm² | 250 A Class T, 95 mm² | 2/0 AWG (175 A) / 250 kcmil (255 A) |
| F4–F6 | Each battery positive | 125 A, 35 mm² | 125 A, 35 mm² | 1 AWG (130 A) |
| S1 | Battery isolator | DC rated, ≥ 160 A, 60 V DC or more | DC rated, ≥ 250 A | Listed DC disconnect |
| – | Negative busbar ↔ shunt ↔ batteries | Same sizes as the matching positive cables | Same | Same |
| C3 | Inverter AC output → output breaker + isolator → board | Output breaker 32 A (= the 48/3000's 32 A transfer switch rating), 4 mm². Set the AC-input current limit to suit the generator. | Output breaker 50 A (= the 50 A transfer switch rating), 10 mm² | 3 kW: 50 A breaker, 6 AWG (transfer switch 50 A on 120 V models). 5 kW split phase: 2-pole 50 A, 6 AWG. |
| – | Generator → inverter AC-in | Per the generator rating and the inverter's input current limit | Same | Same |
The sizes are checked against BS 7671 Appendix 4 / AS/NZS 3008.1.1 ratings for single-core cables in free air, and against NEC 310.16. Your installation method (enclosed in trunking, bundled, hot loft) can lower a cable's rating considerably, so recheck with the method you actually use. In Australia, AS/NZS 3008.1.1:2025 is the current cable-selection edition.
6. Real sun data: what the systems deliver, month by month
The reference systems were simulated with PVGIS 5.3, the European Commission's free solar tool, for six locations. It used 19 years of hourly satellite and weather data, including local horizon shading.
Example daily load
| Load | 3 kW system (6 kWh/day) | 5 kW system (10 kWh/day) |
|---|---|---|
| Fridge-freezer (A-rated) | 0.6 kWh | 0.6 kWh |
| Lighting (LED) | 0.4 kWh | 0.6 kWh |
| TV, router, laptops, phones | 1.0 kWh | 1.5 kWh |
| Washing machine (cold or eco wash, solar hours) | 0.5 kWh | 1.0 kWh |
| Cooking: induction hob, microwave, kettle | 2.0 kWh | 3.5 kWh |
| Water pump, central heating pump or fans | 0.5 kWh | 1.0 kWh |
| Power tools, vacuum, other | 0.5 kWh | 1.0 kWh |
| Inverter standby and losses | 0.5 kWh | 0.8 kWh |
| Total | about 6 kWh/day | about 10 kWh/day |
Space heating and hot water by electricity are left out. They would need several times more energy in a UK winter. Use wood, LPG, a heat pump on a much larger system, or the summer surplus (see using surplus energy).
PV yield per kWp, by month
Average kWh per day from 1 kWp, tilted at about the latitude (steeper in the UK) and facing the equator, with 14% losses:
| Location (tilt) | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Year |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| London (50°) | 1.5 | 2.0 | 2.8 | 3.7 | 3.6 | 3.8 | 3.7 | 3.4 | 3.2 | 2.4 | 1.8 | 1.3 | 1014 |
| Glasgow (55°) | 0.9 | 1.6 | 2.4 | 3.3 | 3.4 | 3.3 | 3.3 | 2.9 | 2.5 | 1.8 | 1.3 | 0.8 | 841 |
| Seattle WA (45°) | 1.7 | 2.5 | 3.3 | 3.8 | 4.0 | 3.8 | 4.4 | 4.4 | 3.9 | 2.9 | 1.9 | 1.5 | 1160 |
| Phoenix AZ (35°) | 4.6 | 5.2 | 5.6 | 5.7 | 5.4 | 5.1 | 4.6 | 4.7 | 5.0 | 5.2 | 4.8 | 4.3 | 1829 |
| Sydney (35°) | 4.5 | 4.4 | 4.2 | 4.1 | 3.9 | 3.3 | 3.8 | 4.4 | 4.9 | 4.8 | 4.6 | 4.6 | 1559 |
| Melbourne (40°) | 4.8 | 4.8 | 4.3 | 3.6 | 2.8 | 2.5 | 2.8 | 3.3 | 4.1 | 4.5 | 4.5 | 4.7 | 1426 |
Whole-system simulation
Each cell shows the average energy delivered per day (kWh) and, beneath it, the percentage of days the battery hit its 10% reserve, which means load shedding or a generator start.
3 kW system: 3.6 kWp, 10 kWh battery, 6 kWh/day load
| Location | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Year |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| London | 3.77 74% | 4.74 55% | 5.58 24% | 5.94 5% | 5.92 5% | 5.98 2% | 6.00 0% | 5.95 2% | 5.90 5% | 5.44 25% | 4.67 56% | 3.80 76% | 27% |
| Glasgow | 2.51 94% | 4.06 69% | 5.27 39% | 5.89 10% | 5.96 3% | 5.97 1% | 6.00 1% | 5.93 3% | 5.67 17% | 4.73 50% | 3.69 78% | 2.36 95% | 38% |
| Seattle WA | 4.13 58% | 5.15 33% | 5.76 10% | 5.99 3% | 5.98 1% | 6.01 1% | 6.00 0% | 6.00 0% | 5.94 1% | 5.62 17% | 4.62 47% | 3.82 67% | 20% |
| Phoenix AZ | 6.00 0% | 6.00 1% | 6.00 0% | 6.00 0% | 6.00 0% | 6.00 0% | 6.00 0% | 6.00 0% | 6.00 0% | 6.00 0% | 5.99 0% | 6.00 1% | 0% |
| Sydney | 5.96 1% | 5.98 0% | 5.95 2% | 5.97 1% | 5.96 2% | 5.88 5% | 5.97 2% | 6.03 0% | 6.01 1% | 6.00 1% | 5.97 0% | 6.03 0% | 1% |
| Melbourne | 6.00 0% | 5.97 0% | 6.00 0% | 5.93 1% | 5.92 4% | 5.87 8% | 5.92 6% | 6.04 1% | 6.02 0% | 6.01 0% | 6.01 0% | 5.99 0% | 2% |
5 kW system: 7.2 kWp, 15 kWh battery, 10 kWh/day load
| Location | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Year |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| London | 6.85 68% | 8.34 48% | 9.49 20% | 9.93 4% | 9.91 3% | 9.99 1% | 10.00 0% | 9.93 2% | 9.91 3% | 9.31 21% | 8.24 46% | 6.96 68% | 24% |
| Glasgow | 4.89 90% | 7.30 64% | 9.15 30% | 9.90 6% | 9.96 2% | 9.99 0% | 10.00 0% | 9.92 2% | 9.66 11% | 8.29 43% | 6.82 70% | 4.65 90% | 34% |
| Seattle WA | 7.38 52% | 8.84 30% | 9.68 9% | 9.97 3% | 9.98 0% | 10.02 0% | 10.00 0% | 10.00 0% | 9.90 2% | 9.54 14% | 8.10 39% | 6.96 61% | 18% |
| Phoenix AZ | 9.99 1% | 10.00 0% | 10.00 0% | 10.00 0% | 10.00 0% | 10.00 0% | 10.00 0% | 10.00 0% | 10.00 0% | 10.00 0% | 9.99 0% | 10.00 1% | 0% |
| Sydney | 9.96 0% | 9.98 0% | 9.94 2% | 9.96 1% | 9.94 2% | 9.82 4% | 9.96 2% | 10.04 0% | 10.01 1% | 10.01 0% | 9.96 0% | 10.03 0% | 1% |
| Melbourne | 10.01 0% | 9.94 0% | 10.00 0% | 9.89 1% | 9.91 2% | 9.86 6% | 9.91 6% | 10.07 1% | 10.04 0% | 10.00 0% | 10.02 0% | 9.98 0% | 1% |
- Sydney, Melbourne, Arizona: both systems cover their loads on 98% or more of days through the year. A generator is an occasional backup for a dull week in winter.
- London, Seattle: self-sufficient from about April to September. From November to February the battery runs flat on roughly a third to three-quarters of days, so a generator, or a much larger array, is essential.
- Glasgow and further north: the winter gap is bigger still. In December and January the systems deliver only about 40–50% of the load on average.
- The days the battery is "full" show that summer has a large surplus. That's the energy to divert to hot water.
Source: PVGIS 5.3 (European Commission JRC), PVcalc and off-grid (SHScalc) tools, queried 13 November 2026. UK: PVGIS-SARAH3. USA and Australia: PVGIS-ERA5. These are long-term averages: plan for runs of poor weather beyond them.
7. Winter autonomy and generator planning
Days of autonomy
Usable battery ÷ daily load = days the system runs with no sun:
- 3 kW system: 10 kWh × 90% usable ÷ 6 kWh/day ≈ 1.5 days
- 5 kW system: 15 kWh × 90% ÷ 10 kWh/day ≈ 1.35 days
Common off-grid targets are 2–3 days where there's a generator, and 3–5 days without one. In the UK, adding battery alone doesn't fix winter: the array can't refill it. Add panels (especially at a steep tilt) and a generator.
Generator run time and fuel, by month
The monthly fuel use in litres needed to cover the shortfall in the simulation above. Assumptions:
- Charge efficiency 90%.
- The generator charges at the inverter's charger rate: 3 kW system 35 A ≈ 1.9 kW; 5 kW system 70 A ≈ 3.8 kW.
- A small inverter generator gives about 1.5 kWh of generator output per litre of petrol at those loads.
| Location | System | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Year: shortfall / run hours / fuel |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| London | 3 kW | 40 | 21 | 8 | 1 | 1 | 0 | 0 | 1 | 2 | 10 | 23 | 40 | 252 kWh / 147 h / 187 L |
| London | 5 kW | 29 | 14 | 5 | 1 | 1 | 0 | 0 | 1 | 1 | 6 | 15 | 28 | 338 kWh / 99 h / 251 L |
| Glasgow | 3 kW | 63 | 32 | 13 | 2 | 1 | 0 | 0 | 1 | 6 | 23 | 41 | 66 | 424 kWh / 248 h / 314 L |
| Glasgow | 5 kW | 46 | 22 | 8 | 1 | 0 | 0 | 0 | 1 | 3 | 15 | 28 | 49 | 592 kWh / 173 h / 438 L |
| Seattle WA | 3 kW | 34 | 14 | 4 | 0 | 0 | 0 | 0 | 0 | 1 | 7 | 24 | 40 | 213 kWh / 125 h / 158 L |
| Seattle WA | 5 kW | 24 | 10 | 3 | 0 | 0 | 0 | 0 | 0 | 1 | 4 | 17 | 28 | 294 kWh / 86 h / 218 L |
| Melbourne | 3 kW | 0 | 1 | 0 | 1 | 1 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 12 kWh / 7 h / 9 L |
| Melbourne | 5 kW | 0 | 1 | 0 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 16 kWh / 5 h / 12 L |
| Sydney | 3 kW | 1 | 0 | 1 | 0 | 1 | 2 | 0 | 0 | 0 | 0 | 1 | 0 | 11 kWh / 6 h / 8 L |
| Sydney | 5 kW | 0 | 0 | 1 | 0 | 1 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 15 kWh / 4 h / 11 L |
| Phoenix AZ | 3 kW | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 kWh / 0 h / 0 L |
| Phoenix AZ | 5 kW | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 kWh / 0 h / 1 L |
Example: in London, the 3 kW system needs about 250 kWh a year from the generator, roughly 150 run hours and 190 litres of petrol, about 85% of it from November to February. In Glasgow that's about 310 litres. In Sydney or Melbourne it's around 10 litres a year.
Automatic generator start
- Use a generator with an electric start and a two-wire remote-start input. Let the inverter or system controller (for example a Victron Cerbo GX) start it on battery state of charge: start at about 30–40%, stop at about 80–90%. Running to 100% wastes fuel on the slow final top-up.
- Add a load-based start, for example above 80% of the inverter rating for 1 minute, so big loads run from the generator rather than draining the battery.
- Set quiet hours (for example 22:00–07:00), a minimum run time (about 1 hour, to warm the engine) and a monthly exercise run.
- Set the inverter's AC-input current limit to the generator's continuous rating so the charger and loads can't overload it.
8. Generator integration
Sizing
- Continuous output ≥ charger input + pass-through load. For the 3 kW system that's about 2.1 kW of charger input plus typical loads, so a 3–4 kVA generator. For the 5 kW system, a 5–8 kVA generator. Use the generator size calculator.
- Inverter generators (stable, clean output, quiet, good fuel economy at part load) work best with inverter/chargers. Some cheap open-frame generators have unstable voltage and frequency, which inverter/chargers reject. If so, widen the inverter's acceptance range only within its maker's limits.
- Diesel generators suit long annual run hours (several hundred or more). Petrol or LPG inverter generators suit occasional use.
Earthing and neutral: the critical detail
When the generator runs, the inverter's internal neutral–earth relay opens. The neutral–earth bond must then come from the generator side, or the RCDs or GFCIs can't detect an earth fault.
| Country | Generator requirements |
|---|---|
| UK | Use a generator with its neutral bonded to its frame and earth terminal, connected to the installation's earth. Or fit a bond at the generator inlet that operates only when the generator is the source. Follow BS 7671 Section 551 (generating sets) and Chapter 82. Use a 30 mA RCD (Type B unless the inverter maker allows Type A) on the generator feed. Never use a floating-neutral site generator on its own. |
| Australia | The generator connects through the inverter AC input. The MEN arrangement must give exactly one N–E link in each mode. AS/NZS 4509.1 and AS/NZS 3010 (generating sets) apply. The electrician designs and certifies the arrangement. |
| USA | NEC Article 445 (generators) and 250.30/250.35. Whether the generator neutral should be bonded depends on whether the neutral is switched and on the inverter's ground-relay design. A common US design keeps one permanent N–G bond at the main panel and leaves the generator neutral unbonded. Follow the inverter's installation manual, make sure there is exactly one N–G bond in every mode, and confirm with the AHJ. |
Installation
- Carbon monoxide kills. Run generators outdoors only, well away from doors, windows and vents, never in a garage, shed or porch. Fit CO alarms in the building.
- Use a weatherproof housing or acoustic enclosure with plenty of airflow. Store fuel safely and legally. Bring the generator lead in through a weatherproof inlet (BS EN 60309-2 or NEMA L14/TT-30, as appropriate).
- Noise: a typical inverter generator produces about 50–60 dB(A) at 7 m. Check local nuisance rules and site it away from neighbours.
9. Fault level, earthing and cable derating
Inverter fault current and protective devices
An inverter, unlike the mains grid, can supply only a limited fault current, often about 2–3 times its rated current for a short time before it shuts down. Check the datasheet. That changes how circuits are protected:
| Device | Magnetic (instant) trip needs | 3 kVA inverter (≈13 A rated; ≈30–40 A fault) |
|---|---|---|
| B6 MCB | 3–5 × In = 18–30 A | Likely trips instantly |
| B16 MCB | 48–80 A | May not trip instantly. It relies on the slower thermal trip, or on the inverter shutting down. |
| B32 MCB | 96–160 A | Won't trip magnetically |
| 30 mA RCD/RCBO | 30 mA earth leakage | Trips for earth faults whatever the fault current |
So: protect every circuit with a 30 mA RCBO (UK/AU) or GFCI breaker (US) for earth-fault and shock protection. Size the MCB parts to the cables as normal. Confirm with the inverter maker that it will shut down safely on a line–neutral short that an MCB doesn't clear. Record the measured fault loop impedance and prospective fault current on the certificate.
Earth electrode
| Country | Target |
|---|---|
| UK | With the inverter providing the N–E link, the system behaves like TN-S, and the electrode stabilises it. Use RA × IΔn ≤ 50 V as a guidance target, as for TT. With a 30 mA RCD that's ≤ 1,667 Ω in theory, but BS 7671 notes that readings over 200 Ω may not be stable. Aim for under 200 Ω, and preferably under 100 Ω. |
| Australia (MEN) | An electrode to AS/NZS 3000 (normally a 1.2 m+ copper-clad rod) at the main switchboard, with the main earthing conductor sized to the standard. Any SPS-specific requirements of AS/NZS 4509.1 also apply. |
| USA | Grounding electrode system to NEC 250. A single rod is acceptable only if it measures 25 Ω or less; otherwise add a second rod at least 6 ft away. |
Measure with an earth electrode tester (3-pole fall-of-potential, or a loop tester on a TT system), in dry conditions if possible, and record it.
Cable derating: a worked example
Cable ratings in tables assume one cable at 30 °C. Grouping cables together and hot places reduce the rating:
- Example: four 4 mm² AC circuits bunched in one trunking in a plant room at 40 °C.
- Base rating 30 A (BS 7671 Table 4D2A, reference method B, two-core).
- × grouping factor 0.65 (4 circuits).
- × ambient factor 0.87 (40 °C, 70 °C PVC).
- = about 17 A. A 20 A or 32 A breaker would no longer protect it. Use 6 mm² (38 A × 0.65 × 0.87 ≈ 21.5 A, fine for 20 A), or separate the runs.
The same applies to DC battery cables run in a hot cabinet. Use 90 °C or 105 °C insulated cable and check the maker's derating tables. AS/NZS 3008.1.1 and NEC 310.15 give the factors for Australia and the USA.
10. Surge and lightning protection
- Why: long PV cables pick up induced surges from nearby lightning strikes. Exposed ground arrays and overhead lines to outbuildings are most at risk. Damage to an MPPT or inverter is the usual result.
- UK: BS 7671 Section 443 requires SPDs where the consequences of overvoltage would be serious, and in other cases unless the owner declares the risk acceptable (a narrow exception remains for single dwellings; check the current edition). Section 534 covers selection. For PV, fit DC SPDs (Type 2, PV-rated, UCPV ≥ the array's cold Voc) at the controller end of long array cables (over about 10 m), and at both ends of very long runs. Fit an AC Type 2 SPD at the main board.
- Australia: AS/NZS 5033 asks for a lightning and surge risk assessment for the PV array. AS/NZS 1768 is the lightning protection standard. Inland, high-lightning areas usually justify DC and AC SPDs.
- USA: NEC 230.67 requires SPDs on services to dwellings. Many AHJs apply the same thinking to stand-alone systems, so ask. NEC 690.41 (system grounding) and 690.43/690.47 (equipment grounding and electrodes) cover PV grounding. Fit PV-rated DC SPDs at the charge controllers on long or exposed runs.
- Good practice everywhere: run PV positive and negative cables together (small loop area), bond array frames to the earth system with short, direct conductors, and keep SPD earth leads as short as possible (under 0.5 m) or they lose their effect. If the building has a lightning protection system, keep the array within its protected zone and get the separation distances designed to BS EN 62305 / AS/NZS 1768 / NFPA 780.
11. Using surplus energy, and adding wind or hydro
Divert the summer surplus to hot water
The simulation shows the battery is full on most summer days (London: 52–63% of days across the year). Once the battery is full, the MPPTs throttle back and the extra energy is wasted. Two ways to use it:
- Relay-switched immersion heater: the system controller (for example a Victron Cerbo GX) switches a contactor feeding an immersion element when the battery's state of charge is above about 95% and solar power is above the element's rating. Use a smaller element (1 kW for the 3 kW system, 2 kW for the 5 kW system) so it doesn't drain the battery on a cloudy spell. Fit a hysteresis or minimum-on time so it doesn't chatter.
- Dedicated PV-to-heat: a separate PV string feeding a DC immersion heater (or a DC-input diverter) directly, independent of the battery system. Use only a DC-rated element, thermostat and thermal cut-out, or a purpose-made DC diverter. An ordinary AC immersion thermostat can't safely break PV DC: it can arc and weld shut.
- With the relay-switched option, the immersion is a normal fixed AC circuit with its own RCBO. The cylinder thermostat and thermal cut-out stay in place.
Adding wind
- Wind complements solar well in the UK: more wind in winter. A small 48 V turbine (400 W–1 kW) connects to the DC busbar through its own charge controller with a dump load. A turbine must never run unloaded, or it overspeeds.
- Fuse the turbine controller's battery cable at the busbar like any other source. Fit a turbine brake or stop switch.
- Siting matters more than size. A turbine needs clear, unobstructed wind, usually on a mast 10 m or more above nearby obstacles. Masts usually need planning permission (UK) or council or permit approval (Australia, USA).
- See the OffGridVolts wind calculators for expected output.
Adding micro-hydro
- Where there's a stream with head (fall) and year-round flow, micro-hydro gives steady energy 24 hours a day. Even 200–500 W continuous is 5–12 kWh a day, enough to transform the winter picture.
- It connects like wind: its own controller with a diversion or dump load, fused at the busbar. Water abstraction and impoundment licences apply (Environment Agency, Natural Resources Wales, SEPA in Scotland or NIEA in Northern Ireland in the UK; state water authorities in Australia; state agencies or FERC exemptions in the USA).
12. United Kingdom
Rules that apply
| Document | What it covers |
|---|---|
| BS 7671:2018+A4:2026 (in force since 15 October 2026) | The whole installation. In particular:
|
| IET Code of Practice for Electrical Energy Storage Systems; IET Guidance Note 7 | Battery system design guidance and PV labelling. |
| PAS 63100:2024 | Fire safety of battery storage in dwellings, including where batteries must not go. |
| Building Regulations: Part P (England and Wales); building warrant (Scotland) | Installing a new consumer unit or new circuits in a dwelling is notifiable. Use a registered competent-person installer who self-certifies, or apply to building control. |
| MCS (MIS 3002, MIS 3012) | Not legally required. It's only needed for some grants and schemes, and for export payments, which an off-grid system can't receive anyway. |
| Planning | Roof PV on a house is usually permitted development. Ground arrays, listed buildings and conservation areas have limits, so check with the local planning authority. |
Earthing: the off-grid system makes its own
- With no DNO supply there's no supplier's earth, so the installation needs its own. Use an earth electrode connected to the main earthing terminal, and one neutral–earth link at the source. The MultiPlus-II makes that link with its internal earth relay whenever it is inverting. Its manual says a Type A RCD can be used on its output.
- Generator mode: the inverter's earth relay opens whenever an AC input is present, so on generator power the N–E link must come from the generator side. Use a generator with a bonded neutral, or make the bond at the generator inlet. Never feed the inverter from a floating-neutral generator, or the RCDs will not see an earth fault.
- There must be only one N–E link in the system. Don't add a second one in the consumer unit if the inverter provides it, or the other way round. Record the earthing arrangement (TN-S from the inverter, or TT) and the electrode resistance on the EIC.
- Protect every final circuit with a 30 mA RCD (RCBOs are neatest). An inverter can supply only limited fault current, often too little to trip an MCB's magnetic element quickly. So the RCD, not the MCB, gives the fast disconnection for earth faults. Check the inverter's short-circuit output against the MCB type and size for line–neutral faults as well.
- If a generator or other AC source feeds the inverter's AC input, the RCD on that supply should be Type B, unless the inverter maker states Type A is acceptable (BS 7671 A4 Chapter 57). Victron says Type A is acceptable for the MultiPlus-II.
Batteries
- PAS 63100 says not to install batteries:
- in rooms for sleeping;
- in escape routes, including landings, stairs and corridors, and in protected escape-route corridors, shafts and lobbies, firefighting lobbies and stairs;
- in cupboards opening into sleeping rooms;
- in voids, roof spaces or lofts;
- within 2 m of stored flammables or fuel;
- in basements with no outside access;
- outdoors within 1 m of escape routes, doors, windows or vents.
- Chapter 57 notices: a battery-presence notice at the consumer unit, and "WARNING – Isolate both AC and DC sides before servicing" on the inverter. Every DC isolator must be rated for DC.
PV side (Section 712)
- A DC switch-disconnector on the DC side of the controller. PV cable to EN 50618. Earth the frames where the module and inverter makers require it.
- Risk-assess surge protection (Sections 443 and 534). Long PV runs to a ground array usually justify SPDs at both ends.
- PV labels: "WARNING – SOLAR PHOTOVOLTAIC SYSTEM" and "contains live parts during daylight" on junction boxes and isolators, as in IET Guidance Note 7.
Certification
An Electrical Installation Certificate (EIC) to BS 7671. Test the PV side to BS EN 62446-1 (polarity, Voc, Isc, insulation resistance). Notify under Part P or apply to building control. Keep the design, datasheets and the shutdown procedure with the system.
13. Australia
Rules that apply
| Standard | What it covers |
|---|---|
| AS/NZS 4509.1:2009 (safety and installation) and AS/NZS 4509.2:2010 (system design) | Stand-alone power systems. A revision is under way, with a new edition expected in 2026. Check whether it has been published before you build. |
| AS/NZS 5033:2021 (as amended) | PV arrays: string voltage, fusing, isolators, cable, earthing, signs. |
| AS/NZS 5139:2019 + Amendment 1 (December 2025) | Battery systems with power conversion equipment: location, barriers, arc-flash, signs, safety data sheet. Amendment 1 is now mandatory. |
| AS/NZS 3000:2018 (Wiring Rules, as amended) and AS/NZS 3008.1.1:2025 | The AC installation, earthing (MEN), RCDs and cable selection. |
| Solar Accreditation Australia (SAA) and the Clean Energy Council (CEC) product lists | To claim STCs under the Small-scale Renewable Energy Scheme, the system needs an SAA-accredited designer and installer with off-grid (stand-alone) accreditation, plus CEC-listed panels and inverters. Off-grid PV is eligible. Installer accreditation moved from the CEC to SAA in 2024. |
Licensing: who can do the work
- Any work above extra-low voltage (above 50 V AC or 120 V ripple-free DC) must be done by a licensed electrician. That covers the 230 V side and the PV strings (about 200 V DC). It must then be certified to the state regulator, for example with a Certificate of Electrical Safety or Certificate of Compliance.
- The 48 V battery side is extra-low voltage, but its fault energy is high, and AS/NZS 5139 still applies to the installation. In practice the whole system is installed and signed off by the licensed electrician.
Earthing and AC protection
- Use a MEN system at the main switchboard, with an earth electrode and a single neutral–earth (MEN) link. If the inverter has an internal N–E relay, set it up as the inverter maker and AS/NZS 4509.1 describe, so there is only ever one N–E connection.
- Fit 30 mA RCDs on final circuits as AS/NZS 3000 requires. Use an AC isolator at the inverter output and a main switch at the switchboard labelled for the inverter supply. Connect a generator through the inverter's AC input. The inverter's N–E relay opens on generator power, so the generator must provide the neutral–earth bond (bonded-neutral generator, or a bond at the inlet), arranged with the MEN so there is only one link in each mode. Fit an output breaker sized to the inverter's transfer switch rating, as in the protection schedule.
Batteries (AS/NZS 5139)
- Restricted locations:
- within 600 mm of an exit, a window or a vent into a habitable room, or an appliance, and within the 900 mm zone below these;
- ceiling spaces, wall cavities and roofs;
- under stairs or walkways;
- escape routes;
- habitable rooms.
- Amendment 1 changes:
- It allows installation within 600 mm of an opening wider than 900 mm, such as a garage door.
- Exempt barrier materials to habitable rooms must be at least 6 mm thick.
- It adds rules for building materials within 1 m of a battery classed as a chemical hazard.
- A physical copy of the safety data sheet must be kept at the battery in a protective pouch.
- Protective devices on paralleled batteries must be rated for the combined fault current.
- Inverters are now treated as associated appliances and may sit within a restricted location.
- Find out the prospective fault current and arc-flash energy from the battery maker. The SEIAPI off-grid guideline, based on AS/NZS 5139, sets three thresholds: domestic systems must stay under 40 cal/cm²; above 4 cal/cm² the battery shouldn't be inside a building with habitable rooms; above 8 cal/cm² it should be split into segments. Confirm these against the standard.
- Required signs: battery-system signs and the shutdown procedure (AS/NZS 5139, AS/NZS 5033), PV array and isolator labels, and a dual-supply notice at the switchboard.
PV side (AS/NZS 5033)
- Work out cold Voc with the module coefficient at the site minimum temperature. Rate isolators, the controller input and cable above it. Use load-breaking DC isolators rated for PV.
- String fuses are needed once there are three or more strings in parallel (rated 1.5–2.4 × Isc and no more than the module's maximum series fuse). Bond the array frames as AS/NZS 5033 requires.
- Design the mounting to AS/NZS 1170.2 for your wind region. Cyclonic regions need single clamps on every module.
14. United States
Rules that apply
| Code / standard | What it covers |
|---|---|
| NEC (NFPA 70), adopted edition (2023 widely, 2026 in some states) |
|
| NFPA 855 / IRC R328 (or the state's version) | Residential battery (ESS) limits and locations. |
| Listings |
|
| Permit and inspection | The local Authority Having Jurisdiction (AHJ). Most require a permit for PV and ESS even when off-grid. Many let homeowners pull a permit for their own home. Otherwise, use a licensed electrician. |
Key US requirements
- Article 710:
- Premises wiring is installed exactly as for a normal service.
- Conductors from the inverter to the building disconnect are sized on the sum of the inverter output ratings.
- The inverter may be smaller than the calculated load, but must be large enough for the largest single load.
- Fit a permanent plaque or directory at the service equipment showing the power sources (710.10).
- 3 kW on a single 120 V inverter: under 710.15(C), a 120 V inverter may supply a 120/240 V panel only if:
- there are no 240 V loads;
- there are no multiwire branch circuits;
- the inverter output breaker is rated below the panel's neutral bus rating.
- Generator mode: the inverter's ground relay opens when AC input is present, so the generator path must provide the neutral-to-ground bond (a bonded-neutral generator, or an arrangement your inspector approves). Exactly one bond in each mode. Fit an output breaker sized to the inverter's transfer switch rating (the protection schedule).
- Grounding: one system bonding jumper (neutral to ground) only, in the panel or in the inverter as its listing requires. Use a grounding electrode system to Article 250, with two rods unless a single rod is 25 Ω or less. Ground the PV frames and racking (690.43).
- Rapid shutdown (690.12): required for PV circuits on or in buildings, off-grid or not. Exempt: ground-mounted circuits that enter a building used only to house PV equipment (Exception 1), and arrays on non-enclosed detached structures such as carports and trellises (Exception 2). If a ground array's circuits enter the house to reach the MPPTs, rapid shutdown applies.
- GFCI and AFCI on branch circuits as for any dwelling (Article 210). Labels and disconnects: PV system disconnect, ESS disconnect and the required placards (690, 706, 710).
- Batteries: each ESS unit ≤ 20 kWh. Total ≤ 40 kWh in a utility or storage room and ≤ 80 kWh in a garage, on an outside wall or in a detached structure. Not in sleeping rooms, or in closets or spaces that open directly into sleeping rooms or habitable spaces (IRC R328). The 10 and 15 kWh banks here are well inside these limits.
- Conductors: PV source circuits at 1.56 × Isc. Battery and inverter conductors from Table 310.16 at the 75 °C terminal rating (sizes in the protection schedule). DC breakers and fuses must be DC rated.
15. Scaling beyond 5 kW
| Step | How | What to check |
|---|---|---|
| 8–10 kW | Parallel two or three identical inverters on one phase, or use one larger inverter (e.g. 8–10 kVA). Use more MPPTs, each with 2 strings. | Battery bank and BMS able to supply the combined continuous and surge current of all the inverters. Equal cable lengths to paralleled inverters. Main fuse and busbar rated for the total current. |
| 10–15 kW and above | Three-phase: one inverter per phase (UK/AU 400 V, USA 208/120 V or 480/277 V), or several split-phase units in parallel. | Phase balance, three-phase loads, and a larger and segmented battery. Australia: arc-flash limits. USA: per-unit and aggregate kWh limits. |
| Batteries > 20–40 kWh | A dedicated battery room or outbuilding. | USA: NFPA 855 Chapters 4–9 above the residential limits. Australia: AS/NZS 5139 location and arc-flash rules. UK: PAS 63100 and the insurer's requirements. |
16. Installation practice and crimping
- Every high-current connection uses a lug matched to the cable and the stud. Crimp it with a hydraulic crimper and the correct hex die, inspect it, pull-test it, seal it with adhesive heat-shrink and torque it to the maker's figure. On the 200 A and 250 A circuits, a bad crimp with just 1 mΩ of resistance gives off 40–63 W of heat at the fuse rating (I² × R), or about 15 W at the 121 A design current, without blowing a fuse. The crimping section of our campervan wiring guide covers this step by step.
- Use bootlace ferrules on fine-strand cable in screw terminals. MC4 connectors must be the same make and type on both halves, crimped with the maker's tool. Never mix MC4 brands.
- Battery cables must not be run in closed conduit (Victron). Keep DC cables short, positive and negative run together, and away from AC wiring.
- Mount the inverter, MPPTs and busbars on a non-combustible board with the clearances the makers specify. Make sure the battery isolator can be reached quickly in an emergency.
- Configure the system: battery profile and charge voltages from the battery maker, and BMS communication (DVCC on Victron) so the battery controls charge current. Set the inverter's low-voltage shutdown and the generator auto-start levels.
17. Testing and commissioning
- Check the polarity of each PV string and its Voc at the isolator. Compare with the expected value for the temperature. Measure Isc or operating current.
- PV insulation resistance to BS EN 62446-1 / AS/NZS 5033: 500 V DC test for strings with Voc between 120 and 500 V, as here; at least 1 MΩ.
- Before connecting the batteries, check continuity and that there is no short between the DC busbars. Check every fuse rating against the schedule, and the torque on every bolted joint.
- Connect the batteries with the isolator open. Check each module's voltage (within about 0.1 V of the others before paralleling). Close the isolator and confirm the BMS is communicating.
- Start the inverter with no load. Check the output voltage and frequency, and the N–E link (exactly one).
- Test the AC installation:
- continuity of protective conductors;
- insulation resistance (disconnect electronics);
- polarity;
- earth electrode resistance;
- earth fault loop impedance on the inverter supply;
- RCD (UK/AU) or GFCI (US) trip tests.
- Load test: run the largest motor load (pump, fridge) and check surge handling. Measure the millivolt drop across the battery and inverter joints at high load, and look for warm lugs after 30–60 minutes.
- Generator test: auto start, transfer, charging current limit, and the RCD on the generator feed.
- Paperwork:
- UK: EIC, BS EN 62446-1 PV test sheet, Part P notification.
- Australia: electrical safety certificate to the regulator, and the CEC/STC paperwork if claimed.
- USA: permit sign-off.
- In every country, keep a system manual and the shutdown procedure on site.
18. Commissioning test sheets
Fill these in as you go and keep them with the system manual. The country-specific certificate (EIC in the UK, the state Certificate of Compliance or CES in Australia, the AHJ sign-off in the USA) is still required. These sheets record the extra off-grid checks.
Sheet 1: PV strings (BS EN 62446-1 / AS/NZS 5033)
| String | Modules | Polarity ✓ | Voc expected (V) | Voc measured (V) | Isc or Iop (A) | Irradiance / module temp | IR + to E (MΩ) | IR − to E (MΩ) |
|---|---|---|---|---|---|---|---|---|
| 1-1 | 4 | |||||||
| 1-2 | 4 | |||||||
| 2-1 | 4 | |||||||
| 2-2 | 4 |
Sheet 2: DC system
| Check | Expected | Result | Initials |
|---|---|---|---|
| Each fuse F1–F7 fitted at the scheduled rating | As schedule | ||
| Breaking capacity of F4–F7 ≥ battery prospective fault current | Maker's figure: ____ kA | ||
| Torque on all DC lugs and busbars (paint-marked) | Maker's Nm | ||
| Module voltages before paralleling | Within 0.1 V of each other | ||
| BMS communication with the inverter (DVCC or CAN) | Online, limits shown | ||
| Charge voltage, current limits and low-voltage cut-off | As battery maker | ||
| Millivolt drop across each high-current joint at about 50% load | < 10–15 mV each | ||
| Thermal check after 30–60 minutes at high load | No hot spots |
Sheet 3: AC system and earthing
| Check | Expected | Result |
|---|---|---|
| Earth electrode resistance | UK < 200 Ω · AU per AS/NZS 3000 · US ≤ 25 Ω or 2 rods | |
| Number of N–E links, inverting | Exactly 1 | |
| Number of N–E links, generator running | Exactly 1 | |
| Inverter output voltage and frequency, no load | 230 V 50 Hz / 120–240 V 60 Hz | |
| Continuity of protective conductors (R1+R2) | Per circuit | |
| Insulation resistance (electronics disconnected) | ≥ 1 MΩ | |
| Polarity at every outlet and device | Correct | |
| Earth fault loop impedance and prospective fault current, inverter source | Record | |
| RCD / GFCI trip time at IΔn | ≤ 300 ms (UK/AU); GFCI trips | |
| RCD on the generator feed (type and trip) | Type B, or Type A where the maker allows | |
| Generator auto-start, stop and quiet hours | As set | |
| Labels, shutdown procedure and safety data sheet in place | Yes |
19. Costs and the grid-connection comparison
These are approximate ranges at November 2026, rounded, for budgeting only. "Equipment" means the parts list in this guide (excluding the generator). "Installed" adds design, labour, mounting, certification and the generator. Prices vary widely, so get quotes.
| UK (£) | USA ($) | Australia (A$) | |
|---|---|---|---|
| 3 kW system, equipment | 7,000–10,000 | 8,000–12,000 | 12,000–18,000 |
| 3 kW system, installed | 12,000–18,000 | 15,000–25,000 | 15,000–30,000 (industry guide figure for 3–5 kW array + 10–15 kWh battery) |
| 5 kW system, equipment | 11,000–16,000 | 13,000–19,000 | 18,000–27,000 |
| 5 kW system, installed | 18,000–28,000 | 22,000–35,000 | 25,000–45,000 |
| Generator (inverter type, 3–8 kVA, remote start) | 800–4,000 | 1,000–5,000 | 1,500–7,000 |
Compared with connecting to the grid
| Country | Typical grid connection cost |
|---|---|
| UK | A simple new domestic connection near the network starts at about £1,300 and averages about £1,800 (Electricity North West indicative costs). Longer distances, overhead line extensions, road crossings and transformer upgrades can take remote sites into many thousands, or tens of thousands, of pounds. |
| USA | About $8,000–15,000 to run 1,000 ft overhead, or $10,000–25,000 underground (roughly $8–25 per foot), plus permits. Line extensions of a mile or more often run well into six figures. |
| Australia | Connecting remote blocks can cost tens of thousands of dollars per kilometre of line. Some distributors now offer network-owned stand-alone power systems (SAPS) instead of rebuilding long rural lines. |
Rule of thumb: if the grid is at the boundary, connecting is usually cheaper. Off-grid becomes competitive once the line extension runs to several hundred metres or more, or where an existing line needs costly upgrading. Then add the value of no electricity bills, minus battery replacement (about every 10–15 years for LiFePO4), generator fuel and maintenance.
20. Troubleshooting chart
| Symptom | Likely causes | What to check or do |
|---|---|---|
| Inverter overload on motor start (pump, compressor) | Surge above the inverter's peak rating. Several motors starting together. | Stagger the starts. Fit a soft-start. Check the inverter's surge rating. Put large motors on the generator through the load-start rule. |
| Battery low by morning in winter | Normal winter shortfall (see the simulation tables). Standby loads. A heater or pump running overnight. | Check daily kWh in the monitoring. Find standby loads with a plug-in meter. Set generator auto-start on state of charge. |
| Generator runs but the inverter won't accept it | Voltage or frequency outside the acceptance window. A bad earth or neutral bond. AC-input breaker tripped. | Check the generator's frequency and voltage under load. Widen the inverter's acceptance range within the maker's limits. Check the N–E bond. |
| RCD trips when the generator connects | Two N–E links (generator plus another bond). Incompatible RCD type. A real earth fault. | Confirm exactly one N–E link in generator mode. Check the RCD type (Type B or as the maker allows). |
| MPPT output low on a sunny day | Battery full (normal, it's throttling back). Shading. A string fault or blown string fuse. Dirty panels. Cold Voc lock-out. | Compare string currents. Check the controller's errors and history. Do a Voc check per string. |
| BMS disconnects | Cell over- or under-voltage, over-current, or temperature. | Read the BMS log. Check charge settings and current limits, and the battery room temperature. |
| Warm busbar, lug or fuse holder | A loose or bad crimp, wrong torque, or an undersized fuse holder. | Isolate, remake, re-torque and re-test with the millivolt drop. |
| Lights flicker on load changes | DC voltage sag on long or thin battery cables. Weak or overloaded generator. | Measure the DC voltage at the inverter terminals under load. Check generator stability. |
21. Maintenance schedule
| When | Task |
|---|---|
| Monthly | Review monitoring (daily kWh, state-of-charge minimum, generator hours). Visually inspect the battery area and inverter vents. Check the generator oil and fuel. |
| Every 3 months | Clean the panels if they're dirty. Check MC4 connectors and cable fixings. Test the RCDs or GFCIs with their buttons. Exercise-run the generator. |
| Yearly | Torque check of all DC joints, thermal scan at high load, and millivolt drops. Battery capacity check from monitoring data. Firmware updates. Generator service (oil, filters, plugs). Re-measure the earth electrode. Check SPD status indicators. |
| Every 3–5 years | Periodic inspection and test of the AC installation: an EICR in the UK, or as recommended locally. Re-check PV string IR and Voc. |
| About 10–15 years | Budget for battery replacement, and inverter or controller replacement or refurbishment. |
22. Labels and signs
| Where | UK | Australia | USA |
|---|---|---|---|
| Main board / switchboard / panel | Dual-supply / alternative-source notice. Battery-presence notice (BS 7671 Chapter 57). Earthing arrangement. | "Solar / battery system" signs and the shutdown procedure (AS/NZS 4509.1, 5033, 5139). Generator signs. | Power source plaque or directory (NEC 710.10). ESS labels (706). The 710.15(C) warning if a single 120 V supply. |
| Inverter | "WARNING – Isolate both AC and DC sides before servicing" | Isolation and shutdown signage per AS/NZS 4509.1 / 5139 | Equipment markings. Disconnect labels. |
| PV isolators and junction boxes | "PV array DC isolator – live during daylight" (IET guidance) | "Solar DC isolator" and "Danger – DC voltage" (AS/NZS 5033) | "PV system DC disconnect" (690.13, 690.53). Rapid shutdown label if applicable. |
| Battery | Battery type, voltage, energy, hazards. No-smoking sign. | AS/NZS 5139 hazard signs, arc-flash label if required. Safety data sheet in a pouch. | ESS labels (706), and NFPA 855 signage where applicable. |
Use durable engraved or UV-stable labels. Exact wording, colours and sizes are in each standard; check the current edition.
23. Frequently asked questions
Is there a legal size limit for an off-grid solar system?
No. The UK's G98/G99, Australian export limits and US interconnection rules only apply to systems connected to the grid. Battery location and size rules (PAS 63100, AS/NZS 5139, NFPA 855) still apply.
Can a 3 kW off-grid system run a house in the UK all year?
Only with a generator. In the PVGIS simulation, a 3.6 kWp / 10 kWh system covers 6 kWh/day from April to September in London, but runs short on most days from November to February. That's about 190 litres of petrol a year through the generator.
Does off-grid work better in Australia?
Much better. In Sydney and Melbourne, the same systems cover their loads on about 98–99% of days, and a generator is only an occasional backup.
Do I need a licensed electrician?
In Australia, yes, by law, for anything above extra-low voltage. In the UK the AC side must be certified to BS 7671, and in a dwelling notified under Building Regulations. In the USA a permit and inspection are normally needed.
Why fuse every battery and add a main fuse?
Fuses in parallel add up. Three 125 A battery fuses could let 375 A into the shared cable without blowing, so a main fuse protects that cable. Each fuse must also be able to break the batteries' combined fault current.
Can I add a wind turbine later?
Yes. Connect it to the DC busbar through its own charge controller with a dump load, fused like any other source. Wind is often strongest in winter, when solar is weakest.
How long do the batteries last?
Typically 10–15 years or 3,000–6,000 cycles for LiFePO4, depending on depth of discharge and temperature. Budget for replacement.
24. Parts list (example)
| Item | 3 kW | 5 kW |
|---|---|---|
| Inverter/charger, 48 V | 1 × 3 kVA (230 V or 120 V) | 1 × 5 kVA (230 V or 120/240 V) |
| LiFePO4 battery modules, 51.2 V 5 kWh with BMS comms | 2 | 3 |
| Solar panels, about 450 W | 8 | 16 |
| MPPT charge controller, 250 V / 70 A | 1 | 2 |
| PV DC isolator, 2-pole, ≥ 250 V DC, ≥ 32 A | 1 | 2 |
| Main battery fuse, Class T with holder | 160 A | 250 A |
| Battery isolator, DC rated | ≥ 160 A | ≥ 250 A |
| Per-battery fuses or breakers (breaking capacity ≥ combined battery fault current) | 2 × 125 A | 3 × 125 A |
| Fused DC busbar (e.g. Lynx Distributor) + negative busbar | 1 set | 1 set |
| Busbar fuses: inverter (F1), MPPT (F2/F3), backed up by F7 | 125 A + 100 A | 200 A + 2 × 100 A (US split phase: 2 × 125 A + 2 × 100 A) |
| AC output breaker | 32 A (US 50 A) | 50 A (US 2-pole 50 A) |
| Battery monitor shunt | 1 | 1 |
| AC output isolator, consumer unit/switchboard/panel with 30 mA RCD/RCBOs (GFCI/AFCI in the US) | 1 | 1 |
| Earth electrode(s), earthing conductor, main earth terminal | 1 set | 1 set |
| Surge protection devices (DC PV and AC), if the risk assessment calls for them | – | – |
| Labels, shutdown procedure, safety data sheets | 1 set | 1 set |
25. Check your own numbers
- Off-grid solar system calculator and power consumption calculator: size the system from your daily use
- MPPT string voltage calculator and solar panel series/parallel calculator: cold Voc and string layout
- Solar charge controller calculator
- Battery bank size calculator and battery run time calculator
- Inverter size calculator and generator size calculator
- DC cable size calculator, fuse size calculator and AWG to mm² converter
- AC voltage drop calculator
26. Sources
- European Commission JRC – PVGIS 5.3 (PV yield and off-grid simulations)
- Electricity North West – Indicative costs of a new domestic connection
- Angi – Cost to run electric service 1,000 ft
- Energy Matters – Off-grid solar system cost in Australia (2026 guide)
- Victron – MultiPlus-II inverter/charger datasheet (continuous VA and W, and peak ratings)
- Victron – MultiPlus-II 230 V installation (DC fuse and cable table, earth relay, Type A RCD)
- Victron – SmartSolar MPPT 250/70 technical specifications
- SEIAPI/PPA – Off-grid PV power systems installation guidelines (AS/NZS based), v3 September 2025
- NSW Government – Changes to the battery standard (AS/NZS 5139 Amendment 1)
- GSES – Habitable rooms and restricted locations for battery installation
- Standards New Zealand – Update of the stand-alone power systems joint standards (AS/NZS 4509)
- SolarQuotes – Wiring without an electrical licence in Australia
- Battery Design – PAS 63100:2024 summary
- BS 7671 and solar PV – UK regulatory guide
- IET Wiring Matters – The impact of Amendment 4:2026
- Florida Solar Design Group – Residential battery ESS size limits (NFPA 855)
- EC&M – NEC requirements for stand-alone power production systems (Article 710)
- Solar Permit Solutions – NEC 690.12 rapid shutdown and exemptions
- Solar Builder – What to know about the 2026 NEC
This guide is guidance for typical systems, not a substitute for a site-specific design. OffGridVolts accepts no liability for installations based on it. Have the installation designed, inspected, tested and certified as your country's rules require.
New to some of the terms? See the glossary. Not sure where to start? Try start here.