Solar for a shed, workshop, allotment or garden office

The step up from a basic DIY kit: a stand-alone solar system to run a garden office or workshop. Covers loads and winter sizing, choosing 12, 24 or 48 V, an example 24 V system, power tools, mounting panels on light structures, battery placement, wiring and earthing the AC side, combining with the mains, and the planning and electrical rules in the UK, USA and Australia.

By Michael Johnson · Updated 16 November 2026 · How we check our guides

This guide is the step up from our DIY solar kit guide: a stand-alone solar system big enough to run a garden office, workshop, allotment shed or cabin, with lights, laptops, a small fridge and power tools. It covers sizing for real winter sun, choosing 12, 24 or 48 V, mounting panels on light structures, wiring a shed like a small house, earthing, and the planning and electrical rules in the UK, USA and Australia.

Mains voltage is the dangerous part. The battery and DC side need correct fusing and crimping, as in our other guides. But once an inverter makes 230 V or 120 V and feeds fixed wiring, sockets and lights, it's an electrical installation like a house, and the rules about who can do the work apply. See section 11.
Related: garden and allotment solar and small solar jobs such as CCTV, fences and gates.

1. What will you run?

LoadPowerTypical daily energy
LED lighting (4–6 fittings)30–60 W0.1–0.3 kWh
Laptop and monitor, 8 hours60–120 W0.5–1.0 kWh
Router or mobile hotspot10–20 W0.2–0.5 kWh
Small fridge50–100 W running0.3–0.6 kWh
Kettle, 3 boils2,000–3,000 W0.2–0.3 kWh
Power tools (saw, drill, sander), 1 hour500–2,000 W0.5–1.5 kWh
Electric heater (1 kW), 6 hours1,000 W6 kWh: not practical on solar in winter

Heating is the deal-breaker. A garden office heated electrically needs a mains supply or a different heat source; see the diesel heater guide and the wood burner guide. Add up your own loads with the power consumption calculator.

2. 12, 24 or 48 V?

System voltageSuitsWhy
12 VUp to about 1–1.5 kW of inverter and 400–600 W of panelsSimple, lots of 12 V kit; but currents get very high (a 2 kW inverter draws about 190 A)
24 VAbout 1.5–3 kW inverter and up to about 1.5 kW of panelsHalf the current of 12 V, cheaper cable and fuses
48 V3 kW and above, or long cable runsA quarter of the current of 12 V; most larger inverter-chargers and server-rack batteries are 48 V

Note that 48 V systems are still extra-low voltage (under 120 V DC) but can deliver huge fault currents. Australian rules require a licensed electrician for anything above 120 V DC, which a series string of solar panels often exceeds; see section 11.

3. An example system

Garden office or workshop: a 24 V stand-alone system About 1.2 kW of panels, 5 kWh of LiFePO4 and a 3 kVA inverter-charger. Every battery positive fused; AC side like a small house. PV array 3 × 400 W (3 in series) PV isolator DC rated MPPT controller 150 V / 60 A DC busbar + battery fuse (Class T or MRBF at terminal) LiFePO4 battery 24 V 200 Ah (5.1 kWh) with BMS fuse Inverter-charger 3 kVA pure sine + battery charger Shed consumer unit main switch · 30 mA RCD / RCBOs sockets · lights · fridge earth electrode (TT) Optional: mains inlet or SWA cable to charge in winter (electrician) Before you start planning (roof or ground panels), building regs / permits, tenancy or allotment rules, insurance, shed roof strength, security Above 120 V DC or 50 V AC (Australia) and on any mains-voltage wiring, the work must be done by a licensed or competent electrician. UK: BS 7671 Sections 712 (PV) and 551 (generating sets) · US: NEC Articles 690, 706, 710 · Australia: AS/NZS 4509.1, 5033, 5139, 3000
A typical 24 V garden office system. The same layout scales to 48 V with a larger inverter.
PartExampleNotes
Panels3 × 400–450 W household panels in seriesCheck the string's cold-weather Voc stays below the controller limit with the MPPT string voltage calculator
Charge controllerMPPT, 150 V input, 60 A output (24 V)Takes up to about 1.7 kW of panels at 24 V
Battery24 V 200 Ah LiFePO4 (5.1 kWh) with BMSAbout 4.5 kWh usable; check with the battery bank size calculator
Inverter-charger3 kVA (about 2.4 kW) pure sine, 24 VRuns a saw or kettle; charges from a generator or mains in winter
DC protectionClass T or MRBF fuse at the battery; fuses for each circuit; DC isolatorSee the fuse size calculator and DC cable size calculator
AC sideSmall consumer unit with main switch, 30 mA RCD protection, MCBs or RCBOsInstalled and tested by a qualified electrician (section 8)

4. Sizing for winter

5. Power tools and big loads

6. Mounting panels on sheds and in gardens

7. Where the battery goes

8. Wiring the shed: the AC side

9. Earthing a stand-alone system

10. Combining with a mains supply

11. Planning and electrical rules by country

UKUSAAustralia
PlanningEngland: solar on houses and outbuildings in a house's grounds is usually permitted development, with limits on stand-alone (ground) arrays and in conservation areas and on listed buildings. The rules for houses changed on 27 August 2026 (SI 2026/896), with a 12-month transition; check the Planning Portal. Wales, Scotland and Northern Ireland have their own rulesZoning rules for accessory structures and ground-mounted arrays (setbacks, height); HOA rules may apply, though many states limit HOA bans on solarCouncil rules; many states treat small rooftop solar and some sheds as exempt or complying development within set limits (for example NSW exempt development rules)
Electrical rulesBS 7671 (IET Wiring Regulations), including Section 712 (PV) and Section 551 (generating sets); MCS for grid-connected systems claiming export paymentsNEC Article 690 (PV), 706 (energy storage), 710 (stand-alone systems), 480 (batteries); UL-listed equipmentAS/NZS 4509.1 (stand-alone power systems), AS/NZS 5033 (PV arrays), AS/NZS 5139 (batteries), AS/NZS 3000 (wiring rules)
Who can do the workEngland and Wales: Part P applies to installations in dwellings and in outbuildings supplied from them; new circuits are notifiable, normally through a registered electrician. Work must meet BS 7671 whoever does it. A stand-alone extra-low-voltage system is less regulated, but its mains-voltage side should still be installed and certified properlyElectrical permit and inspection in most jurisdictions; some allow homeowners to do their own work with a permitAny work above 50 V AC or 120 V ripple-free DC must be done by a licensed electrician (state licensing laws). Mechanical work, like fixing panels and racks, isn't electrical work
Allotments and rentalsAllotment tenancy rules often limit structures and equipment; ask the council or association. Tenants need landlord consentCommunity garden and lease rulesCommunity garden and lease rules; council approval for structures

12. Security, damp and maintenance

13. Approximate costs

SystemUKUSAAustralia
12 V, 400 W panels, 1.3 kWh battery, 1 kW inverter (parts)£900–1,500$900–1,600A$1,500–2,500
24 V, 1.2 kW panels, 5 kWh battery, 3 kVA inverter-charger (parts)£2,500–4,000$2,500–4,500A$4,000–6,500
Electrician for AC side and testing£300–900$500–1,500 plus permitA$500–1,500

Rough 2026 prices; they vary widely.

14. Frequently asked questions

Can I run a garden office on solar power all year?

In sunny climates, yes for lights, computers and a small fridge. In the UK, winter solar output is so low that most garden offices also need a mains charger or generator, and electric heating is impractical on solar.

Do I need planning permission for solar panels on my shed?

In England, panels on outbuildings within a house's grounds are usually permitted development, but limits apply to stand-alone arrays, conservation areas and listed buildings, and the rules for houses changed in August 2026. Check the Planning Portal or your council. US and Australian rules depend on your local council or zoning.

Is 12 V or 24 V better for a shed solar system?

12 V suits small systems up to about 1 kW of inverter. For anything bigger, 24 V or 48 V halves or quarters the current, making cables, fuses and connections cheaper and safer.

Can I wire my shed's sockets myself?

In Australia, no: work above 50 V AC or 120 V DC needs a licensed electrician. In the UK, the work must meet BS 7671 and new circuits in outbuildings supplied from a house are notifiable under Part P in England and Wales. In the US, most areas require a permit and inspection.

Does a stand-alone solar shed need an earth rod?

Usually yes, once it supplies mains-voltage sockets: there's no network earth, so the system needs its own earth electrode connected to the inverter and consumer unit. An electrician should design and test it.

15. Sources

  1. Planning Portal, changes to permitted development rules for domestic solar (August 2026): planningportal.co.uk
  2. UK legislation, General Permitted Development Order 2015, Schedule 2 Part 14: legislation.gov.uk
  3. IET, Part P (England and Wales) frequently asked questions: theiet.org
  4. Government of Western Australia, renewable energy systems and electrical licensing factsheet (2024): wa.gov.au
  5. Standards Australia, AS/NZS 4509.1 stand-alone power systems: standards.org.au
  6. Australian Government ABLIS, AS/NZS standards for solar PV systems: business.gov.au

General guidance only. Mains-voltage wiring must be installed and tested by a qualified or licensed electrician in line with the rules where you live.